NamPPF II: Power to Namibia
The approximately 500km Auas–Kokerboom transmission line, linking the Auas substation near Dordabis with Kokerboom near Keetmanshoop, is intended to strengthen the national grid by improving reliability, stability and redundancy, while increasing the capacity to transfer electricity between the north and south. It will also strengthen Namibia’s ability to participate in regional electricity trade, i.e. also feed into the Southern African Power Pool.
NamPower’s current project estimate is approximately N$2 billion. The Environmental Clearance Certificate (ECC) has been issued, while design, route and wayleave matters have been part of the preparatory work. The project is therefore moving towards the procurement and construction stages.
The November 2023 environmental and social assessment had put the estimated cost at a minimum of N$990 million, calculated at N$2.2 million per kilometre. That difference illustrates how important it is to work with updated project estimates as planning now progresses. The earlier assessment envisaged a construction period of approximately three years.
This is a substantial undertaking, but it should also be viewed as an opportunity to strengthen local industry. The line will require specialised engineering, construction capacity, materials, logistics and skilled labour. Some components will inevitably have to be sourced internationally, but that does not mean that the entire project should be imported – this expertise is available in Namibia.
Namibian capacity
One company illustrating the potential is Power Line Africa (PLA), a Namibian transmission-line contractor headquartered in Tsumeb. The company says it has completed more than 20 transmission-line projects in Namibia, including work on 220kV, 330kV and 400kV infrastructure. In 2017 PLA specifically built a 400kV transmission line (such as Kokerboom) between Kunene and Omatanda. Apart from numerous further projects in Southern Africa, PLA has commissioned more than 30 transmission lines and/or substations in the Democratic Republic of Congo (DRC) alone. Its website lists ISO 9001, ISO 14001 and ISO 45001 certifications.
In August 2024, PLA was among 19 companies appointed to South Africa’s National Transmission Company of South Africa (NTCSA) overhead transmission-line construction panels. The programme was reported to have an estimated value of approximately SAR32 billion over eight years. That appointment is significant, as it shows that a Namibian company can qualify for work in a much larger and highly competitive electricity market.
Whether it be hydrogen, gas or oil, Namibia and foreign investors currently invest heavily into education and training. In the case of construction of transmission lines, Namibia already has the expertise, it simply needs to hold onto- and expand it. When investing into transmission-infrastructure, the government should ideally employ local expertise – not dissimilar to any other expertise in the construction industry.
Striking comparison in SA
Former Eskom (SA) chief executive André de Ruyter made a striking comparison in his book published in 2023, Truth to Power: My Three Years Inside Eskom: “If Eskom wants to build a transmission line, we pay a whopping two and a half times more per kilometre than NamPower does in neighbouring Namibia.” He was able to make that comparison after PLA had become involved in a South African project for a while. De Ruyter’s South African experience raises serious questions about procurement costs, corruption and the consequences of inefficient contracting – cost discipline, capable local suppliers and a transparent procurement are key.
The objective should not be to exclude foreign companies. Namibia needs international capital, technology and specialist expertise. But the country should not be dependent on foreign contractors who arrive with their own people, infrastructure and supply chains as soon as an apparently big project looms on the horizon. Properly structured partnerships can combine international expertise with local capacity, skills transfer and sustainable employment, thus not leaving Namibian businesses with only a marginal share of the work.
NamPower has proven local capability
Albeit a parastatal, NamPower itself is an example of what a strong Namibian institution can deliver. Its 2025 Integrated Annual Report recorded revenue of N$9.1 billion, total assets of N$59 billion and capital expenditure of N$2.9 billion. The company reported transmission-system performance of 99.81%, with no load-shedding or power outages during the reporting period.
NamPower remains responsible for generation, transmission, distribution, supply and electricity trading as one integrated utility. South Africa, by contrast, has unbundled Eskom into three separate entities dealing with generation, transmission and distribution.
NamPower's Integrated Strategic Business Plan for 2026–2030 recognises that the scale of future investment requires partnerships and additional funding avenues. It identifies public-private partnerships as an underused opportunity and envisages engagement with private companies to increase confidence in strategic electricity projects.
Localised logistics
The company has also made progress in local procurement. Its 2025 report records N$1.6 billion in localised preferential procurement, compared with N$629.8 million in the previous financial year. Through its NamPower Equitable Economic Empowerment Policy (NEEEP), it encourages joint ventures and subcontracting to Namibian-owned businesses. On the Anixas II project, actual local-content spending reached 15.32%, exceeding the original 15% commitment.
This is the sort of approach that should become increasingly important as Namibia expands its electricity infrastructure. NamPower's success demonstrates that local institutions can operate to demanding standards, manage complex systems and deliver reliable services. The next step is to ensure that this capacity is reflected more consistently throughout the supply chain. Why should the still meagre 15% local participation not aim to become 100%, if such expertise is available locally?
A question for the NamPPF
This is where the second Namibia Public-Private Forum (NamPPF) event becomes particularly relevant. The discussion should go beyond the familiar call for foreign investment. It should ask how Namibia can attract the capital and expertise it needs while building its own companies, contractors, suppliers and skilled workforce.
Every major infrastructure contract is also an economic decision. When local firms are meaningfully involved, more of the project’s value can circulate through Namibian wages, suppliers, training, taxes and reinvestment. When the work is largely imported, a substantial share of that value as well as the future dividends may leave the country.
Power Line Africa is an example of the kind of Namibian capacity that deserves serious consideration. This is not an argument for awarding contracts without competition or for lowering technical standards. It is an argument for giving qualified local companies a fair opportunity to compete, to partner with international firms and to grow alongside the country’s infrastructure.
The Auas–Kokerboom project offers a timely opportunity to put that principle into practice. NamPower has shown what Namibia can achieve by developing and maintaining its own institutional capacity. If the country wants to keep pace with the increasing demands of a modern electricity network, it must also develop and use the local companies capable of building it.
The central question at NamPPF is: How do we move from simply procuring infrastructure to building a stronger Namibian industry around it?